Scope of Work & Estimate — Crawlspace Encapsulation
5868 Montpelier Drive
$6,575.96 Partial Encapsulation Option — Scope of Work & Estimate · 10% discount applied
5868 Montpelier Drive · Williamsburg, VA 23188
Partial Encapsulation — 10 Mil Vapor Barrier · Dehumidifier · Optional Upgrades Available
View PDF — Estimate #1395 Accept & Pay Deposit Estimate valid until September 22, 2026
Project Overview
Customer: Scott Tillem
Project: Crawlspace Encapsulation (Partial or Full)
Address: 5868 Montpelier Drive, Williamsburg, VA 23188
Options: Partial or Full Encapsulation
Estimate #: 1395 (Partial) / 1396 (Full)
Crawlspace: 1,300 sq ft
Perimeter Walls: 140 linear ft
Height: 36" average
Inspection: Moisture in the subfloor and insulation — joists inspected, structurally sound
Choose Your Option
Option 1 ✓ Selected
Partial Encapsulation
Clean up (including the old insulation) · new 10 mil vapor barrier · dehumidifier with pump · electrical with permit · new crawlspace door · optional upgrades available
$6,575.96 10 Mil Barrier Option — Estimate #1395 · 10% discount applied (was $7,306.63)
Option 2 ✓ Selected
Full Encapsulation
Everything in the partial, upgraded to a 20 mil liner up the walls and around the piers, plus foam board wall insulation, R-19 rim joist insulation, vent sealing and the insulation permit · mold treatment available as an optional add-on
$12,693.26 20 Mil Liner Option — Estimate #1396 · 10% discount applied (was $14,103.63)
Only ONE of the two options applies — select the one you prefer. The scope, payment schedule and terms below follow your choice.
1 · Crawlspace Encapsulation — Partial
  • Clean Up & Debris Removal — Clean up of the 1,300 sq ft crawlspace — debris, trash and abandoned material removed and hauled off for disposal (1,300 sq ft)
  • Remove Old Insulation — Existing floor insulation removed from the joist bays, bagged and hauled off (1,300 sq ft) — Included
  • Vapor Barrier — 10 Mil — New 10 mil vapor barrier installed over the full 1,300 sq ft crawlspace floor, measured and cut on-site, staked and secured (1,300 sq ft)
  • Crawlspace Door — New crawlspace door made of PVC board installed in the existing opening (1)
  • Electrical Outlet — Electrical breaker with GFCI outlet and light for the dehumidifier — includes the electrical permit and inspection (1)
  • Dehumidifier with Condensation Pump — AprilAire E100 dehumidifier with companion condensate pump, supplied and installed (1)
  • General Conditions — Permits, protection of the home during the work and daily clean-up (1)
Crawlspace Encapsulation — Partial$6,575.96
2 · Optional Upgrades — Priced Separately
Mold Treatment — Antimicrobial mold treatment applied to the floor structure, joists and subfloor (1)+$1,000.00
Insulation Install — R-19 — New R-19 batt insulation installed between the floor joists over the full 1,300 sq ft (1,300 sq ft)+$2,275.00
Optional add-ons — not included in the total above; take either or both. Both together: +$3,275.00 · total with both: $9,850.96. Optional items bill 50/50 as well.
Project Samples
Site Photos — Before Work
Payment Schedule
Deposit to Schedule
50%
Upon signing — $3,287.98
Final Payment
50%
Upon completion — $3,287.98
10% Customer Discount applied to the project total (−$730.67 Partial · −$1,410.37 Full). Payment schedule: 50% deposit to schedule, 50% balance on completion (optional upgrades are billed 50/50 the same way). Check is a preferred method · Pay by credit card: request.plastiq.com/pay-tidewater-home-improvement-llc (Virtual Affirm credit card not eligible)
Terms & Conditions

SCOPE OF WORK — PARTIAL ENCAPSULATION
Clean Up & Debris Removal: Clean up of the 1,300 sq ft crawlspace — debris, trash and abandoned material removed and hauled off for disposal (1,300 sq ft)
Remove Old Insulation: Existing floor insulation removed from the joist bays, bagged and hauled off (1,300 sq ft) — Included (no charge)
Vapor Barrier — 10 Mil: New 10 mil vapor barrier installed over the full 1,300 sq ft crawlspace floor, measured and cut on-site, staked and secured (1,300 sq ft)
Crawlspace Door: New crawlspace door made of PVC board installed in the existing opening (1)
Electrical Outlet: Electrical breaker with GFCI outlet and light for the dehumidifier — includes the electrical permit and inspection (1)
Dehumidifier with Condensation Pump: AprilAire E100 dehumidifier with companion condensate pump, supplied and installed (1)
General Conditions: Permits, protection of the home during the work and daily clean-up (1)

OPTIONAL UPGRADES — quoted separately (not included in the total above):
Mold Treatment — Antimicrobial mold treatment applied to the floor structure, joists and subfloor (1): +$1,000.00
Insulation Install — R-19 — New R-19 batt insulation installed between the floor joists over the full 1,300 sq ft (1,300 sq ft): +$2,275.00
Optional total: +$3,275.00 — total with the optionals: $9,850.96 (50/50 billing available).

NOT INCLUDED:
- Structural repairs — the floor joists were inspected on site and found structurally sound; no sistering or replacement is included
- Kitchen mid-span beam — quoted separately if you want it
- Plumbing
- Hardwood floor, tile or subfloor replacement
- Work not described above

Notes:
**No active leak was found — the moisture is ambient humidity sitting against the floor structure. Clean-up, treatment and a good liner with a dehumidifier is what brings it under control and keeps it there.
**The floor is particle board, so keeping the crawlspace dry protects it from swelling and soft spots.
**Existing mold growth goes dormant once the crawlspace is dried out.
**The crawlspace will be accessible for storage after completion.
**Jobsite will be left clean once completed.
**Contractor is not responsible for damage caused inside the home while repairing the foundation.

Warranty:
**12 months workmanship on the project.
**5 years on the dehumidifier.

Payment Terms:
Total Project Cost: $7,306.63
10% Customer Discount: -$730.67
Total Project Cost: $6,575.96
50% deposit to schedule the work: $3,287.98
50% balance on completion: $3,287.98
Optional upgrades are billed the same way — 50% to schedule, 50% on completion.
Check is a preferred method.
**You can pay by credit card using the link below.
request.plastiq.com/pay-tidewater-home-improvement-llc
Cards not eligible for payment: Virtual Affirm credit card